苦战六个月!南充这四条路改造提升工程将于今年底前竣工

苦战六个月!南充这四条路改造提升工程将于今年底前竣工
Urban road renovation and upgrading project, with a total planned investment of 356 million yuan.

At the time when the urban road reconstruction was carried out to enhance the tough battle, the Jialing District set up a military order of "satisfying six months and rejoicing the Spring Festival." The district adopted a road of “problem found in the first line, contradictions in the first line, and work in the first line”.

70ad7a4bc17e4abcb8ededbdc7fdfeab

Gathering public opinion, scientific design and transformation content

On July 3, the author came to the construction site of the reconstruction project of Changcheng Road. I saw that the workers were busy working with the crane to carry the rain and sewage pipeline. The excavator on the side was carrying out the cushioning operation on the ditch. “We designed the rainwater pipe diameter to be 1.2m to 2.4m and implemented sub-division drainage, which can completely cure the urban sickness of the city.” Yang Fuzhou, deputy director of the Jialing District Urban and Rural Planning and Construction Bureau said.

This year, the district plans to upgrade the drainage network of Changcheng Road, install a rainwater pipe with a length of about 5 kilometers, a diameter of DN300-DN1500, and a sewage pipe with a length of about 4 kilometers and a diameter of DN400-DN800. A rainwater pipe with a length of about 7 kilometers and a diameter of DN300-DN1500 and a sewage pipe with a diameter of about 5 kilometers and a diameter of DN400-DN800 are buried in Chenshou Road and Dusit Road to ensure the safe and normal operation of the drainage facilities after the completion of the project. The purpose of water pollution and protection of the water environment.

xx城市道路的升级是一次恢复和全面转型。绿化工程,道路改造,电线敷设,路灯照明和公交车站建设是这次升级的重要内容。在绿化和转型方面,该区城乡规划建设局在早期通过问卷调查,广泛征求公众意见。它决定保留Dulu路的中央绿化带和街道树木,并将中央绿化带从4米扩大到7米。长城道和段路两侧的分区将被取消,一些形成不良的街道树木和陈寿路的所有街道树木将被更换,以确保车辆畅通,增强品味城市。为了解决城市居民水压不足的问题,在设计方案中,可以增加一条新的2公里供水管,辐射5平方公里的居民区。为了应对K形交叉路口车辆与行人之间混合交通的问题,增加了一个新的C形人行天桥,以确保人员和车辆的畅通。

“负责领导和建设部门的领导多次进行现场实地调查,组织专家组,从路面,绿化,地下管线,智能交通等方面不断展示和调整,然后进行优化和改进。嘉陵区城乡一体化委员会。最后,在3月12日,对设计方案进行了审查。“杨福州介绍说,在地质勘探,方案制定,施工图设计等方面,区委,区政府将采取长远眼光,争取卓越,确保规划和设计科学合理。

提前计划及时清除施工障碍

7月8日上午8点,工作高峰期,在紫甫路与滨江南路交叉口,长城路,星火路,陈寿路,杜斯特路的施工图和车辆绕行路线图特别引人注目的是,车辆,行人都在交警的指挥下。

事实上,早在建设开始前一个月,嘉陵区委,区政府多次组织协调会议,及时与交警,公交部门对接,制定了车辆绕行路线临时调整方案。巴士路线,以最大限度地方便市民。同时,它通过微信,广播和电视等平台广泛宣传。南湖街道办事处和星火街办事处也组织了该组织,并向各社区分发了3万多份传单,向公众宣传并寻求他们的理解和支持。

“为了确保树木的成活率,我们自今年3月开始移植树木。到5月底,完成了720多棵苗木移植和超过1,420棵树木。”嘉陵区城乡规划建设局工作人员陈洪坤介绍说,除了苗木移植外,还应提前拆除路灯,交通信号灯,监控,公交站点等,以消除道路改造的障碍。重建。

此外,建设部门还加强了与水,电,气,通讯等单位的协调,先进现场勘探,并标明原管道,防止施工过程中管道受损。

为了使招标过程公开,公平,公正,实现“零投诉”,项目的前期准备工作时间大大缩短。道路设立了项目工作组和前线指挥部,以便及时有效地促进工作协调。

快节奏的项目建设加快了

“明天会下雨。为了防止挖掘出的壕沟倒塌,今晚必须完成这一层!” “赶紧通知商业搅拌站,提前下订单,让他们准备好材料并立即发送给他们。”. 6月30日晚9点,总部的改造和翻新工程陈寿路和杜鲁路灯火通明。甲方代表,主管代表,施工人员,安全人员和技术人员正在制定晚会工作计划,以协调和解决相关问题。

After receiving the task, Bi Xingwen, a construction engineer of Chenshou Road and Dusong Road, immediately organized the construction of concrete cushions overnight, and pumped and drained the 4-meter-deep water puddle. In order to ensure the smooth progress of all work on the night, the owners' representatives and supervisors are busy carrying out mass mediation and publicity work on safety matters. Everyone worked together for more than three hours and poured the 50-meter mat at 11 o'clock that night.

“Everyone on the construction site eats lunch every day and continues to work after dinner. Due to the large underground pipe network of Chenshou Road, the construction is difficult. The departments of water, electricity, gas, and communication send special personnel to guard the scene every day to timely deal with the underground caused by construction. Pipe network problem.” Bi Xingwen introduced that the construction party organizes the construction strictly according to the time schedule and process flow. Every day at 10 am, supervisors and field representatives go to the site to count machinery, personnel and materials, and then report them. The leaders in charge of the district will supervise and supervise the construction site every day. The municipal and district supervisory offices will conduct assessments on the situation of Party A, the supervisory party, the construction party, the progress of the project and the quality and safety.

As the original spoil landfill has reached saturation, on the afternoon of June 24, the Jialing District Committee Government organized a project construction material support coordination meeting to clarify that the three docks in Maoershan, Linjiang and Hexi Townships are gravel. Dedicated to the station, and registration of the transport vehicle number plate, obtain the priority of sandstone material supply, and fully guarantee the supply of sand and gravel. The designated Foyeyan Village of Mujiao is a special spoil ground, and timely resolves contradictions and disputes, and demarcates the dedicated lines of the spoil ground.

xx“为了抓住施工期,掌握进度,材料,人员,机械等都是事先准备好的,所有的工作面都完全启动,并同时推广,实现无缝对接。”甲方代表任Bin介绍了项目部门进行地图操作和任务。分解为每月和每周,为了清除当天的任务,问题在当天被清除。每天晚上,项目将定期召开会议,在同一天解决项目推广过程中出现的问题,并安排第二天工作任务的部署。陈寿禄于6月16日开工建设。 7月4日,破碎的路面提前被打破。沟槽开挖和人行天桥桩基工程均达到预期进度。下一步将继续埋设陈寿路西侧的雨水管。网络。

道路建设达到预期目标,陈寿路,杜斯特路雨水管网安装工作已经完成。南充日报)